B2B Trail Construction Updates
M-52 Trailhead – Restoration work is almost complete at the new trailhead, including planting trees, bushes and butterfly seeding areas. Additional installations include a bench, picnic table, bike rack and bike repair station. The installation of the pit toilet is scheduled for early October to complete work at the trailhead.
Frog Island and South Grove Trail projects/City of Ypsilanti – Construction has begun on the South Grove Road trail segment with the removal of the old sidewalk and the installation of the new concrete path. Work on this segment will continue through late September and then work on the Frog Island trail segment will begin.
North Hydro and North Grove/Ypsilanti Township – Asphalt and concrete work is complete on these two segments. Slope restoration work will be complete in late September, and we anticipate opening these two trail segments in October.